ACCL Kenya Project – Bill of Quantities (BOQ) Review

Posted by:

In a break from the daily training clases, Dave Parker and Professor Edwards go over the Bill of Quantities, a required procedural step between the Foreman and the Contractor representative.  The purpose is to make sure that all necessary material has been ordered and will be on site when required.  Because the MAS building time line is less than 1 week, any delay in material can cause a day by day slip in completion.

 

 